Current Report

2015.12.30
Current report 39/2015
Conclusion of annexes to the credit agreements with mBank S.A.
Read more
2015.12.22
Current report 38/2015
Closing advance payment guarantees issued to OGP Gaz-System S.A.
Read more
2015.12.09
Current report 37/2015
Agreement on the settlement of the contract entitled: Construction of the pipeline DN700 Szczecin-Gdańsk
Read more
2015.12.03
Current report 36/2015
Acceptance of the application ZRUG Zabrze S.A. for not culpable delay in the contract for the construction of the pipeline DN700 Szczecin-Gdańsk
Read more
2015.10.30
Current report 35/2015
Conclusion of contracts for supply of steel products from ArcelorMittal Commercial Sections S.A.
Read more
2015.10.09
Current report 34/2015
Signing of the final acceptance of the pipeline DN700 Szczecin-Gdańsk, Phase II-IV
Read more
2015.10.07
Current report 33/2015
Conclusion of an annex to the investment loan agreement with PKO BP S.A.
Read more
2015.10.07
Current report 32/2015
Extension of the loan agreement with PKO BP S.A.
Read more
2015.09.10
Current report 31/2015
Extension of validity of the guarantee for the proper performance of the contract "Construction of the pipeline DN700 Szczecin-Gdańsk"
Read more
2015.09.09
Current report 30/2015
Extension of validity of the warranty relating to the contract "Construction of the pipeline DN700 Szczecin-Gdańsk"
Read more
2015.08.31
Current report 29/2015
Reduction of the value of the advance payment guarantees issued to OGP Gaz-System S.A.
Read more
2015.08.11
Current report 28/2015
Conclusion of contracts for supply of steel products from ArcelorMittal Commercial Sections S.A.
Read more
2015.07.31
Current report 27/2015
Information on estimated negative impact of financial result of ZRUG Zabrze S.A. for the first half of 2015 on the Stalprofil S.A. Capital Group's results
Read more
2015.07.15
Current report 26/2015
Extension of validity of the warranty relating to the contract "Construction of the pipeline DN700 Szczecin-Gdańsk"
Read more
2015.06.12
Current report 25/2015
Conclusion of contracts for supply of steel products from ArcelorMittal Commercial Sections S.A.
Read more
2015.05.29
Current report 24/2015
Conclusion of an annex to the loan agreement with Pekao SA
Read more
2015.05.13
Current report 23/2015
Extension of validity of the warranty relating to the contract "Construction of the pipeline DN700 Szczecin-Gdańsk"
Read more
2015.04.21
Current report 22/2015
Conclusion of contracts for supply of steel products from ArcelorMittal Commercial Sections S.A.
Read more
2015.04.17
Current report 21/2015
Shareholders holding at least 5% of votes at the AGM of Stalprofil SA on 16.04.2015
Read more
2015.04.16
Current report 18/2015
Adoption of a resolution by the Annual General Meeting of Stalprofil SA on the payment of dividend for 2014
Read more
2015.04.16
Current report 20/2015
Resolutions adopted by the Annual General Meeting of Stalprofil SA
Read more
2015.04.16
Current report 19/2015
Stalprofil SA Supervisory Board appointment for the next term
Read more
2015.04.08
Current report 17/2015
Extension of validity of the warranty relating to the contract "Construction of the pipeline DN 700 Szczecin-Gdańsk"
Read more
2015.04.01
Current report 16/2015
Conclusion of annexes to loan agreements with mBank S.A.
Read more
2015.03.27
Current report 14/2015
Stalprofil SA Supervisory Board recommendation concerning the proposed distribution of profit for 2014
Read more